Our Featured Projects
Chirisa Technology Parks
Lancaster, PA
PROJECT TYPE: DESIGN 350MW SUBSTATION
PROJECT DATE: Start April 2026 – June 2027 (est.)
OVERVIEW:
A complete design of construction power and main substations being fed by four PPL 138kV transmission lines serving twelve 34.5kV feeders for the Chirisa Technology Parks Data Center.