Encompass designed and provided construction management services to Wapakoneta for the Pratt Substation in Wapakoneta that was finished in 2019. The substation is a 69/12.47 50 MVA Station. The station serves a 25 MW cardboard recycling plant plus other community loads. Encompass provided all site, civil, structural, electrical and system design for the substation. The City of Wapakoneta also constructed much of the substation and Encompass provided on-site assistance during the construction efforts to help manage the construction project.
​
​